Waiting for your answers... Answer the following work problem. Report your answer to the nearest tenth of a week. Leslie can do a certain job in 8 weeks. Juan can do the same job in 6 weeks.If Leslie and Juan work together to complete the same job, how many weeks will it take for them to complete it? weeks
Leslie can do a certain job in 8 weeks. Juan can do the same job in 6 weeks.If Leslie and Juan work together to complete the same job, how many weeks will it take for them to complete it?