Waiting for your answers... Answer the following work problem. Report your answer to the nearest tenth of a month. Mary can do a certain job in 8 months. Joe can do the same job in 7 months.Mary and Joe work together to complete the same job. However, Mary starts working 1 months after Joe starts to work. How many months will it take for them to complete the job once Joe starts to work? months
Mary can do a certain job in 8 months. Joe can do the same job in 7 months.Mary and Joe work together to complete the same job. However, Mary starts working 1 months after Joe starts to work. How many months will it take for them to complete the job once Joe starts to work?