Waiting for your answers... Answer the following work problem. Report your answer to the nearest tenth of a week. Leslie can do a certain job in 8 weeks. Petra can do the same job in 9 weeks.Leslie and Petra work together to complete the same job. However, Leslie starts working 5 weeks after Petra starts to work. How many weeks will it take for them to complete the job once Petra starts to work? weeks
Leslie can do a certain job in 8 weeks. Petra can do the same job in 9 weeks.Leslie and Petra work together to complete the same job. However, Leslie starts working 5 weeks after Petra starts to work. How many weeks will it take for them to complete the job once Petra starts to work?