Waiting for your answers... Answer the following work problem. Report your answer to the nearest tenth of a month. Joe can do a certain job in 11 months. Petra can do the same job in 8 months.Joe and Petra work together to complete the same job. However, Joe starts working 4 months after Petra starts to work. How many months will it take for them to complete the job once Petra starts to work? months
Joe can do a certain job in 11 months. Petra can do the same job in 8 months.Joe and Petra work together to complete the same job. However, Joe starts working 4 months after Petra starts to work. How many months will it take for them to complete the job once Petra starts to work?