Waiting for your answers... Answer the following work problem. Report your answer to the nearest tenth of a week. Shawna can do a certain job in 11 weeks. George can do the same job in 10 weeks.Shawna and George work together to complete the same job. However, Shawna starts working 3 weeks after George starts to work. How many weeks will it take for them to complete the job once George starts to work? weeks
Shawna can do a certain job in 11 weeks. George can do the same job in 10 weeks.Shawna and George work together to complete the same job. However, Shawna starts working 3 weeks after George starts to work. How many weeks will it take for them to complete the job once George starts to work?