Delayed Start Work Word Problems
Review the Lesson | MATHguide homepage Updated June 18th, 2023

Waiting for your answers...

Answer the following work problem. Report your answer to the nearest tenth of a month.


David can do a certain job in 10 months. Henry can do the same job in 11 months.

David and Henry work together to complete the same job. However, David starts working 3 months after Henry starts to work. How many months will it take for them to complete the job once Henry starts to work?


months