Waiting for your answers... Answer the following work problem. Report your answer to the nearest tenth of a day. Juanita can do a certain job in 5 days. Mary can do the same job in 9 days.Juanita and Mary work together to complete the same job. However, Juanita starts working 1 days after Mary starts to work. How many days will it take for them to complete the job once Mary starts to work? days
Juanita can do a certain job in 5 days. Mary can do the same job in 9 days.Juanita and Mary work together to complete the same job. However, Juanita starts working 1 days after Mary starts to work. How many days will it take for them to complete the job once Mary starts to work?