Delayed Start Work Word Problems
Review the Lesson | MATHguide homepage Updated June 18th, 2023

Waiting for your answers...

Answer the following work problem. Report your answer to the nearest tenth of a month.


Alice can do a certain job in 7 months. Juan can do the same job in 11 months.

Alice and Juan work together to complete the same job. However, Alice starts working 4 months after Juan starts to work. How many months will it take for them to complete the job once Juan starts to work?


months