Waiting for your answers... Answer the following work problem. Report your answer to the nearest tenth of a day. Frank can do a certain job in 10 days. Joe can do the same job in 9 days.Frank and Joe work together to complete the same job. However, Frank starts working 4 days after Joe starts to work. How many days will it take for them to complete the job once Joe starts to work? days
Frank can do a certain job in 10 days. Joe can do the same job in 9 days.Frank and Joe work together to complete the same job. However, Frank starts working 4 days after Joe starts to work. How many days will it take for them to complete the job once Joe starts to work?