Waiting for your answers... Answer the following work problem. Report your answer to the nearest tenth of a week. Frank can do a certain job in 7 weeks. George can do the same job in 8 weeks.Frank and George work together to complete the same job. However, Frank starts working 4 weeks after George starts to work. How many weeks will it take for them to complete the job once George starts to work? weeks
Frank can do a certain job in 7 weeks. George can do the same job in 8 weeks.Frank and George work together to complete the same job. However, Frank starts working 4 weeks after George starts to work. How many weeks will it take for them to complete the job once George starts to work?