Delayed Start Work Word Problems
Review the Lesson | MATHguide homepage Updated June 18th, 2023

Waiting for your answers...

Answer the following work problem. Report your answer to the nearest tenth of a year.


Shawna can do a certain job in 11 years. Thadeus can do the same job in 9 years.

Shawna and Thadeus work together to complete the same job. However, Shawna starts working 1 years after Thadeus starts to work. How many years will it take for them to complete the job once Thadeus starts to work?


years