Waiting for your answers... Answer the following work problem. Report your answers to the nearest tenth of a week. When Juan and David work together to complete a job it takes them 8 weeks. However, when David works alone, it takes 4 weeks longer than when Juan works alone.How long would it take Juan and David to do the job if each of them works alone?Juan's solo rate is weeks.David's solo rate is weeks.
Answer the following work problem. Report your answers to the nearest tenth of a week.
When Juan and David work together to complete a job it takes them 8 weeks. However, when David works alone, it takes 4 weeks longer than when Juan works alone.How long would it take Juan and David to do the job if each of them works alone?